>>64368171
This isn't Fincantieri, it's the fucking Navy. They didn't even finish designing the class when the start-construction deadline hit. Instead of finishing the design and just taking the hit on the delay, they tried to save face and have Mariette Marine start building before they even had any of the finalized modules. The whole point of the Constellation was to take an off-the-shelf design and run with it, but after picking the FREMM, the Navy went retarded and started making changes to literally everything. At this point, it almost would have been faster to go with a clean sheet design.
Navy officers in charge of the program are literally lying to Congress about how things are going. If the problem was with the builder, the Navy would sell them out. Instead, the Navy is blatantly lying to save their own skin. Marinette Marine didn't have any problems turning out LCS ships, but all of a sudden they don't know how to weld on the Constellation?
The GAO has reported that the problems are the from the Navy constantly asking for major redesigns and then refusing to spend the money to test them, as they are required to by the laws that allocated funding to them. The design doesn't even have any finished fucking plans.
>>64368456
How is it the shipyard's problem when the Navy doesn't even have a finished fucking design? Every time the yard submitted a finished design, the Navy demanded more changes. The original design was supposed to be ~40% different. Now the design is ~85% different. It's total retardation by the Navy. Picrel is the problem. Rear Admiral Tom Anderson, former project manager for the LCS and current retard of charge of Constellation.
>>64368565
>Pay has been climbing
Last time I looked at this a few months ago, Marinette Marine was paying welders the same as the assistant manger of the local weed store and house cleaners. They aren't competing with white collar, they're competing with literally everyone and coming up short.