>"This drives me crazy with the opening of the road to Požega. Every day it will be tomorrow. I expected it to be opened tomorrow. I expected it to be tomorrow, but it probably won't be tomorrow. Whether it will be on Saturday or Sunday, it has to be by Monday. It's not worth it, some paper is always missing because someone didn't sign something and now it's already foiling. The hill moves 0.1 millimeter when you twist it by 0.1 millimeter and I don't know, but that's how it goes - everyone is trying to stop the state," said Aleksandar Vučić.
>But the state of construction of this highway is far more serious. Because the engineers unanimously refused to sign the documents, which are a prerequisite for confirming that the section is completed. Only after that would follow a possible positive report from the Commission for Technical Review, which is the basis for the section to be put into trial operation.
>The biggest problem is the Munjino Brdo tunnel. The terrain above the retaining wall, the already secured landslide near this tunnel is settling, and the hill is full of water.
>"You can see how much water there is. We can see that the water is constantly pouring out of the tunnel. And it goes down further into the river," says Aleksandar Antović.
>Aleksandar Antović, a resident of the village of Prilipac, which is located near this tunnel, tells N1 that the engineers know how big a problem the hill through which the tunnel passes is, and how active the landslide is.
>"They told us, and they were not allowed to bring it to the public, that they have a big problem with the landslide. You can see that they are still working on solving that problem. The last three years have been extremely dry, that landslide is working. The hill through which the tunnel passed is full of water," says Antović.
So, 16 people isn't enough to satisfy his thirst for blood, this fucker now wants to see a highway tunnel collapse.
>But the state of construction of this highway is far more serious. Because the engineers unanimously refused to sign the documents, which are a prerequisite for confirming that the section is completed. Only after that would follow a possible positive report from the Commission for Technical Review, which is the basis for the section to be put into trial operation.
>The biggest problem is the Munjino Brdo tunnel. The terrain above the retaining wall, the already secured landslide near this tunnel is settling, and the hill is full of water.
>"You can see how much water there is. We can see that the water is constantly pouring out of the tunnel. And it goes down further into the river," says Aleksandar Antović.
>Aleksandar Antović, a resident of the village of Prilipac, which is located near this tunnel, tells N1 that the engineers know how big a problem the hill through which the tunnel passes is, and how active the landslide is.
>"They told us, and they were not allowed to bring it to the public, that they have a big problem with the landslide. You can see that they are still working on solving that problem. The last three years have been extremely dry, that landslide is working. The hill through which the tunnel passed is full of water," says Antović.